Major Projects Snapshot
Revised 11/24/2025
| PROJECT NAME | COST | SQ. FEET | CONSTRUCTION START | OCCUPANCY |
|---|---|---|---|---|
| Zucrow High Speed Propulsion Lab | $73M | 54,500 | December 2022 | December 2025 |
| Chilled Water Capacity Enhancements | $65.5M | 1,600 | April 2024 | June 2026 |
| Music Center Addition (Purdue Fort Wayne) | $22M | 26,000 | September 2024 | July 2026 |
| South Hall | $149M | 252,500 | March 2024 | August 2026 |
| Calumet Residence Hall (PNW) | $29M | 42,000 | April 2025 | August 2026 |
| Birck Nanotechnology Clean Room Modernization/New Equipment | $49M | 20,000 | March 2024 | December 2026 |