A. Prior Approvals Needed From Sponsor
(1) Change in Scope or Objective - Performing Organizations in which scientific or other technical effort is sponsored by grants are encouraged to discontinue or modify unpromising lines of investigation, or to explore interesting leads which may appear during the development of the program. NSA must, however, be consulted prior to any changes that might lead to significant deviations from the objectives or overall program of the original effort. Such changes should be proposed to the Program Manager by the PI in a written communication countersigned by the PI's Authorized Organization Representative. If approved by the CO, the Agreement will be amended to reflect the change.
(2) Change in Key Personnel - the Performing Organization will immediately inform the CO when it appears that the PI will not be able to devote substantially the time proposed or otherwise fulfill the agreed commitment to the project. Written approval of the CO will be required to change the PI or to continue the effort during a period of more than three months without the participation of an approved PI.
(3) Foreign travel - Must be specifically approved for each separate trip whether itemized in the budget or not.
(4) Domestic travel - When exceeding the amount allotted by $500 or 25% whichever is greater.
(5) Equipment - Purchase of general purpose equipment not itemized in the budget. Purchase of nonexpendable property not in the budget, and purchase of nonexpendable property costing $5,000 or more with a useful life of at least 2 years and not itemized in the approved budget, or which exceeds the allotted amount by 25 percent.
(6) Land - Expenditures for the acquisition of land or any interest therein.
(7) Consultants - Expenditures for the utilization of the services of consultants not previously provided for under the agreement or itemized in the budget.
(8) Printing - Expenditures for printing and binding unless otherwise specified in the agreement.
(9) No Cost Extension - Any request for extension of the agreement must be submitted in writing by the Performing Organization to the CO. Mutually agreeable time extensions will be effected by written modification to the agreement. Requests for extensions exceeding six months must be accompanied by a revised cost estimate indicating the planned use of unexpended funds during the extension period.
(10) Preaward Costs 90 Days or Less - All requests for preaward costs must be approved by the sponsor.
(11) Any approvals required by OMB Circular A-110