Spring 2008

Project List

Click on the project name below to be taken to the map.

No. BLDG Official Title or Description Constr. Start Date Constr. Finish Date
0A VOIN Upgrade Phone Line Service In Pavilion Area 03/01/08 04/01/08
0 LFPU Beering Drive Sub Drain Installation 5/12/08 8/1/08
1 PKT Pi Kappa Psi New Building: Private Construction 01/01/06 10/01/09
2 HLTP Hilltop Apartments Sewer Lining-2008 05/12/08 07/29/08
2 HLTP Hilltop Apartments Sidewalk and Curb Replacement 05/12/08 08/01/08
3 LAF Steam line Repair- Beering and Ross-Ade 04/01/08 05/12/08
4 LFPL Tower Drive Parking Lot Fence Installation and Landscaping 3/19/08 5/1/08
5 OWEN Owen Side Entrance Door Replacement-2008 5/27/08 7/22/08
6 CQW CQW Exterior Masonry Repair 05/12/08 08/04/08
7 CARY CARY Spitzer Court Landscaping 5/15/08 5/15/08
8 LFST UTTL Cary/Lambert Steam Line Repair 05/13/08 05/20/08
9 LFPM Stadium Mall Gateway 02/22/08 08/15/08
10 CIVL CIVL Exterior Masonry Repair and Replacement 05/12/08 08/01/08
11 PHYS Physics Building Partial Roof Replacement-2007 05/14/07 06/09/08
11 PHYS Physics Building Switchgear and Bus Feed Repair 05/12/08 05/29/08
11 PHYS PHYS- Exterior Masonry Repair and Replacement-2007 05/12/08 08/01/08
12 WILY WILY East Entry Stair Replacement-2008 05/12/08 08/01/08
13 JNSN JNSN- Exterior Masonry Repair 05/12/08 08/04/08
14 LFPM LFPM Purdue Mall Landscaping 3/28/08 3/13/09
15 RSC RSC Center Racquetball Courts 1-16 Air Conditioning Improvements 3/28/2008 3/31/2008
16 WILY Res Hall Food Service Consolidation Phase IV (Wiley Dining Court) 2/19/2008 5/30/2008
17 SSA1 SSA-1 Abate Asbestos from SSA1 02/18/08 03/14/08
18 LFST High Pressure Steam Upgrade at 3rd and Vawter and HPN 05/12/08 08/01/08
19 MGL MGL High Voltage Improvements 01/07/08 04/18/08
20 WIND Windsor Residence Hall Renovation Phase 1- Wood Hall 06/04/07 7/011/08
21 MATH Math Building Electrical Service For Cell Phone Vendors 10/10/07 01/18/08
21 MATH Math Building Transformer Upgrade 03/05/08 12/05/08
22 SC SC-Exterior Masonry Repair and Replacement 05/12/08 07/29/08
23 WTHR Wetherill Laboratory of Chemistry Electrical Upgrade 02/18/08 02/24/08
23 WTHR WTHR High Voltage Improvements 05/15/08 08/11/08
24 GRIS Grissom Hall Recaulk, Tuck-point and Replace Deteriorated Brick 05/12/08 08/01/08
25 HARR Harrison Hall Site and Landscape Improvements 05/14/08 08/01/08
26 WIND Windsor Residence Hall Renovation Phase 2- Wood Hall 06/04/07 07/11/08
27 LAF McCutcheon -Harrison Site Development 05/14/07 04/01/08
28 LFPU Residence Hall Replacement Student Housing-2006 05/21/07 05/22/09
29 MTHW Mathews Hall Sections A-D Roof Replacement 05/12/08 08/04/08
30 STEW STEW West Entry Door Replacement -2008 05/12/08 08/01/08
31 STEW STEW High Voltage Improvements (NE-NW and West Vault) 01/07/08 04/18/08
32 LAF LAF Memorial Mall Landscaping 3/24/08 5/2/08
33 PMU PMU Loading Dock Renovation 05/14/08 07/18/08
34 HIKS HIKS Undergrad Library Investigate and Repair Existing Leaks 05/12/08 08/01/08
35 LFPU Russell Street Utility Tunnel Top Replacement 04/14/08 10/01/08
36 LILY Lilly Hall Window Well and Guardrail Repairs 05/12/08 07/30/08
37 AGAD Agriculture Administration Building Center for Student Achievement and Leadership 3/25/2008 8/15/2008
38 PGM PGM Double Tee Repair 11/21/07 01/09/08
38 PGM PGM Exterior Façade Repair Haunches 05/08/08 08/01/08
39 KRAN KRAN Building Roof Replacement-2008 05/12/08 08/04/08
40 YONG Yong Exterior Recladding 04/11/08 04/09/09
41 PGW PGW Renovation 05/12/08 08/01/08
42 WL Western Sewer Interceptor Phase II ONGOING ONGOING
43 PVIL Purdue Village Telecommunication Upgrade Phase II 7/9/07 2/18/08
44 PVCC Purdue Village Community Center 10/08/07 07/15/08
45 PJIS Patty Jischke Early Care and Education Center 10/08/07 07/15/08
45 PJIS PJIS Install Playground Equipment 5/15/08 6/30/08
46 BRK Birck Nanotechnology AWN Enclosure 05/14/08 08/08/08
47 DISC DISC Temporary Signs 2/6/08 3/3/08
48 MANN MANN Hall  Add a Canopy over North Door 1/17/08 3/11/08
49 PVIL Purdue Village Window Replacement Phase II 05/15/07 08/01/08
49 PVIL Purdue Village Apartments Window Replacement Phase III 05/12/08 08/01/08
50 DISC DISC Adjust Site Development 4/1/08 5/23/08
51 DISC Discovery Park Site Development Phase VI 11/05/07 08/01/08
52 DLC Discovery Learning Center 04/14/08 08/17/08
53 HOCK Wayne T. and Mary T. Hockemeyer Hall of Structural Biology 10/08/07 08/07/08
54 LFEI Harrison Street Aerial Line Relocation Phase 1 - 2008 5/12/08 8/15/08
55 LAF South Russell Street Repair 03/31/08 07/31/08
56 LYNN Lynn And Food Science Parking Lot Landscaping 3/3/08 4/30/05
57 LYNN Lynn Hall Exterior Masonry Vent Repair and Restoration-2008 05/12/08 08/04/08
58 FREH FREH Replace 300KVA Power Transformer in G60 Vault 02/25/08 04/17/08
59 ZL1 Zucrow Labs Z1-Z4 Masonry Restoration - 2008 5/12/08 8/4/08
60 HGR4 Hanger 4 Roof Repair NW Corner 5/16/08 6/30/08
61 NISW NISW Aviation Technology Academic Building 12/20/07 05/29/09
62 AERO Aerospace Science Lab Roof Repair -2008 05/12/08 08/04/08
63 PRSV Printing Services Landscaping-2007 2/18/08 6/27/08
64 LAFX Coal Building Addition -2007 05/12/08 08/01/08

 

For additional campus disruptions, please visit the Travel Alert site:
http://www.purdue.edu/physicalfacilities/travelalert.php.


 

 
purdue homepage
purdue search purdue maps purdue directories

Copyright © 2005, Purdue University, all rights reserved.
An equal access/equal opportunity university.
Purdue University, West Lafayette, IN 47907 USA, (765) 494-4600