Project Name: Physics Building Partial Roof Replacement
Location: Northwestern Ave.
Start Date: 05/14/07
Projected Completion Date: 06/09/08 __________________ Project Name: Physics Building Switchgear and Bus Feed Repair
Start Date: 05/12/08
Projected Completion Date: 05/29/08 __________________ Project Name: Physics Building Exterior Masonry Repair and Replacement
Projected Completion Date: 08/01/08