Project Title: Lilly Hall West Wing Laboratory Renovations Phase V - 2009
Project ID: 9849
Client: Office of the University Architect
Scope:
Phase 5 is the renovation of the main floor of the west wing of Lilly Hall of Life Sciences (resuming Repair and Rehabilitation renovations begun prior to 2001). This project will have three phases of construction in order to accommodate the users occupation of spaces and to maintain egress to those space not being renovated. Renovation to include labs, offices, corridors, restrooms, and stairwells. Supply air and exhaust air systems also will be upgraded.
Construction Start: June 15, 2009
Construction Finish: September 30, 2010
Project Manager: Barb Mansfield
Design & Engineering by: BSA LifesStructures
Construction Work by: TBD
Contract Manager: Chris Marks
Location: State St. and S. Russell Dr.
Map:
|