HIGH VOLTAGE PROJECT

Wetherill Lab of Chemistry

Schedule | Milestones | Photos

Schedule:

  • Construction phase: May 12 - August 15, 2008

Milestones:

  • Beginning the week of April 21, crews will be pulling high voltage cable from the North Power Plant under Central Drive to Wetherill Hall. These cables will power the temporary substations that will be placed at the northwest corner of WTHR during the High Voltage Project.

    During the latter part of next week, Central Drive will be closed for one day to allow crews to install the cable in the tunnel that runs under the road. Signs will be posted and an announcement will be made when the exact date has been determined (either Wednesday, Thursday, or Friday.) Vehicles that park in the HPN/ENAD lot will need to access it from the north side.
  • The vault expansion and equipment upgrades at Wetherill are expected to last from May 12 through August 15, 2008. During that time, the area between WTHR and the North Power Plant will be fenced off for the contractor lay down area. The walkway on the south side of HPN is expected to be maintained. The temporary substations will be in a fenced off area on the northwest side of WTHR, near the bike racks and adjacent to Centennial Mall.  Central Drive will be closed for much of this project. A map of the area can be seen here: http://www.purdue.edu/physicalfacilities/pdf/wthr.pdf
  • Shutdown: The electrical service to WTHR will be shutdown on Tuesday, May 13, 2008, at 6:15 p.m. and will be off for 3-6 hours. This shutdown is required to hook up the temporary substations for the vault upgrades.
Photos:  

road closure
Central Drive north of WTHR will be closed during the high voltage improvements project.

from HPN
This area will be fenced off the week of April 21 as crews pull cable to the temporary substations from the North Power Plant.
contractor area
This entire area will be fenced off for the contractor lay-down area once construction begins in May.
fenced area
This area will be fenced off for the cables running to the substations. The bike racks will be moved just south and still be available.
substations
The grassy area and part of Centennial Mall will be fenced off to contain the temporary substations during the high voltage project.
vault expansion
When the vault expansion begins, construction will take place in this area on the north side of WTHR, which will require Central Drive to be closed.

 
   
 
purdue homepage
purdue search purdue maps purdue directories

Copyright © 2005, Purdue University, all rights reserved.
An equal access/equal opportunity university.
Purdue University, West Lafayette, IN 47907 USA, (765) 494-4600