HIGH VOLTAGE PROJECT
Stone Hall
Schedule | Milestones | Photos
Schedule:
- Bid date: October 12, 2006
- Board of Trustees meeting: November 10, 2006
- Construction phase: January 22 to April 27, 2007
|
 |
Milestones:
- The south (State St.) entrance to Stone Hall will be closed for the duration of the project.
- The sidewalk outside this entrance will be removed. It will be replaced after this project is complete.
- The drive leading to the delivery dock at Stone will be accessible. Brief closures may be necessary on a few occassions.
- January 16 : The mobile substations have been set in place. Most of the State St. side of Stone Hall has been fenced off, and the entrance has been closed.
- January 21: An electrical shutdown will begin at 7:30 a.m. The STON shutdown will last 3-4 hours. During the shutdown, crews will connect STON to the mobile substations.
This shutdown will affect a feeder requiring a brief shutdown of SEAN, SERV, ABE, RES Halls Dishes, WBAA & Educational Dishes, and SMTH. All buildings except for Stone will have power restored in approximately 30 minutes. At the end of the shutdown, SEAN, SERV, ABE, RES Halls Dishes, WBAA & Educational Dishes, and SMTH will experience another brief shutdown, lasting approximately 30 minutes. COMPLETE.
- January 25: See exterior photos below.
- February 1: The old electrical equipment has been removed from the vault. Crews are preparing to move a drain in the floor, and they will soon begin excavating around the outside of the vault. A new concrete pad will be poured.
- February 27: The excavation of the area outside the vault is complete. See photos below. The demolition of the old electrical equipment inside the vault is done, and the new concrete footers and pads have been poured. In the next two weeks, the new transformers and switches will be set in place, and the concrete walls for the vault expansion will be poured.
- March 1: The transformers and switch were lowered into the vault by crane today. View the slideshow here.
- March 13: The vault walls have been formed and poured. The electrical equipment has been installed, and the bus duct installed.
- March 27: The excavated area outside the vault has been backfilled to within a foot of topsoil. One ductbank has been installed and the second is in process. The high voltage electrical work should be complete in the next two weeks. This project is on target to be complete by the end of next month.
- April 10: The ductbank installation is complete. The high voltage wire has been installed and terminated. The vault top is expected to be poured and installed this week. See photos below.
- April 24: Construction is nearly complete. The final electrical shutdown at Stone Hall is scheduled for Sunday, April 29, 2007 beginning at 5 a.m. The shutdown will last about two hours. This is required to remove the mobile substation and restore permanent power to the building. This shutdown will also include the feeder that affects SERV, SEAN, ABE, SMTH, and the Satellite Farm for approximately 15 minutes between 5 and 5:30 a.m. COMPLETE.
- Photos of the new equipment in the upgraded vault are available below.
|
Exterior Photos: 
The State St. entrance to Stone will be blocked throughout the project.
|

The sidewalk on the north side of State St. in front of Stone Hall will remain open. |

The fenced area in front of Stone.
|

|

Two of the three mobile substations. The mobile subs take the place of the transformers in the vault while the vault upgrades take place. |

The third mobile substation. These mobile subs serve both Stone and Matthews Halls. |

The sidewalk on the west side of Stone remains open. |

Secondary cables run from the mobile subs at Stone to the electrical equipment at Matthews. These cables are either fenced or covered with protective handicap accessible ramps. |

The handicapped accessible ramps allow pedestrians to safely cross the cables.
|
|

Feb. 27: A large area around the vault has been excavated to enable the vault repairs and expansion to be constructed. |

At the bottom of the excavated area, the base of the vault expansion is in place. |

A view of the south side of Stone Hall.
|
|

April 9: The excavated area has been backfilled.
|
 |
Interior Photos: 
BEFORE: Aging equipment in the electrical vault at Stone. |

The vault ceiling shows signs of deterioration. |

These transformers will be replaced with new, updated transformers. |
|

AFTER: These photos show the new transformer, cables, and conduit in the upgraded vault. |
 |

|

|
|