High Voltage Project
Smith Hall
Schedule | Milestones | Photos
Schedule:
- Construction phase: May 28 - August 10, 2009
Milestones:
- Shutdown: There will be an electrical shutdown on Thursday, May 14 at 5:30 p.m. Crews will be installing the mobile substations, which will be used to provide power to Smith Hall for the duration of this project. This power outage will affect SMTH for 2-4 hours; SEAN, SERV, ABE, and the ED/WBAA microwave dishes will also be without power for 1-2 hours during this time.
- Fencing has been installed around the sidewalk between Smith and Lilly Halls. A pathway around the fence remains accessible and the entrances at both buildings remain open. See a map of the area here (PDF).