Project Title: Intercollegiate Athletic Facility Football Locker Room Renovation
Project ID: 11131
Website Status Update
The functions previously performed by the Office of the University Architect (OUA) are now addressed by Physical and Capital Planning (P&CP), Project Management and Construction (PM&C), and Energy and Engineering Services (EES). The P&CP website is available here. The Energy and Engineering Services website is available here. A new PM&C website is currently under development, however, essential information will be maintained in this location until the new website is launched. Thank you for your patience as these enhancements are completed.
Client: Athletics
Scope: Remodel football locker room.
Construction Start: May 4, 2010
Construction Finish: July 3, 2010
Project Manager: Tom Walgamuth
Design by:
Job Order Contractor: OCM, LLC.
Location: N. University Dr.
Map:
|