Project Title: Campus-Wide Utility Tunnel Repairs and Waterproofing Phase 1C (Third Street)
Project ID: 9927
Website Status Update
The functions previously performed by the Office of the University Architect (OUA) are now addressed by Physical and Capital Planning (P&CP), Project Management and Construction (PM&C), and Energy and Engineering Services (EES). The P&CP website is available here. The Energy and Engineering Services website is available here. A new PM&C website is currently under development, however, essential information will be maintained in this location until the new website is launched. Thank you for your patience as these enhancements are completed.
Client: Office of the University Architect
Scope:
Repair the interior and along the exterior of the ultility tunnel along State St., beginning just east of Pfendler Hall, north to PSYC, including the Third St. tunnel from Russell to the alley east of Russell.
Construction Start: April 12, 2010
Construction Finish: September 17, 2010
Project Manager: Barb Mansfield
Design & Engineering by: CE Solutions Inc.
Construction Work by: Kettlehut Co., Inc.
Location: State St. and Third St.