Project Title: Roger B. Gatewood Wing of the Mechanical Engineering Building
Project ID: 2734
Website Status Update
The functions previously performed by the Office of the University Architect (OUA) are now addressed by Physical and Capital Planning (P&CP), Project Management and Construction (PM&C), and Energy and Engineering Services (EES). The P&CP website is available here. The Energy and Engineering Services website is available here. A new PM&C website is currently under development, however, essential information will be maintained in this location until the new website is launched. Thank you for your patience as these enhancements are completed.
General Information | Contacts | Location | Project Updates | Photographs
General Information
Client: College of Engineering, Mechanical Engineering Department
Scope:
This project will construct an 84,500 GSF addition on the southwest exposure of the existing Mechanical Engineering building. The addition will house a 120-seat classroom, teaching labs, instructional space, breakout spaces for the Prototype Engineering And Realization Lab (PEARL), faculty and graduate student offices, a graduate and an undergraduate commons, research labs, and a tech-atrium. The addition also will be designed to be the University's first LEED-certified building.
Notes: Please check the Travel Alert page for updated traffic information.
Additional Projects at this site: 9846 ME Utilities Relocation
Construction Start: April 20, 2009
Construction Finish: April 22, 2011
Return to top.
Contacts:
Design & Engineering by: Scholer Corporation
Construction Work by: R.L. Turner
Return to top.
Location: South side of Purdue Mall, on the southwest side of ME
Map:

Return to top.
The construction traffic route to the site is from State Street through Centennial Mall. Concrete barriers have been placed to divide the traffic route from the pedestrian route. Pedestrians are asked to use the west side of the mall (near Stanley Coulter).
Please use caution
near the construction area.
See photos of fencing, traffic reroutes, and construction below.
Project Updates:
- October 5
- Activities Scheduled for next two weeks:
- Footer installation
- Foundation wall installation
- Installation of sanitary and storm pre-cast sumps
- Damp-proofing foundation wall
- Backfill
- Underslab plumbing
- PLEASE NOTE: Steel deliveries are expected to start the week of October 12. This will involve longer semi-trailer trucks, two arriving each morning and two each afternoon. This will be in addition to the ongoing concrete truck and occasional dump truck traffic.
Return to top.