Project Title: Michael Golden Laboratories Gutter and Downspout Replacement and Masonry Repairs - ARRA - 2010
Project ID: 11331

Website Status Update

The functions previously performed by the Office of the University Architect (OUA) are now addressed by Physical and Capital Planning (P&CP), Project Management and Construction (PM&C), and Energy and Engineering Services (EES). The P&CP website is available here.  The Energy and Engineering Services website is available here. A new PM&C website is currently under development, however, essential information will be maintained in this location until the new website is launched. Thank you for your patience as these enhancements are completed.

Client: Project Management & Construction

Scope: Complete window replacement started in 2009. Remove and replace windows at the northwest corner of the first floorof PRCE.

Construction Start: July 12, 2010

Construction Finish: July 30, 2010

Project Manager: Travis Robinson

Design & Engineering by: Physical Facilities

Construction Work by: Scholer Corp.

Location: Third St.