Project Title: Brown Laboratory of Chemistry Foundation Drainage and Waterproofing
Project ID: 10907

Website Status Update

The functions previously performed by the Office of the University Architect (OUA) are now addressed by Physical and Capital Planning (P&CP), Project Management and Construction (PM&C), and Energy and Engineering Services (EES). The P&CP website is available here.  The Energy and Engineering Services website is available here. A new PM&C website is currently under development, however, essential information will be maintained in this location until the new website is launched. Thank you for your patience as these enhancements are completed.

Client: Office of the University Architect - Campus Planning

Scope: Repair and waterproof foundation wall, complete other repairs to divert water from foundation, repair surface drains, replace topping slab and waterproof underground rooms B151/151A/151B, between BRWN and HEAV. Repair and reset the brick pavers between BRWN and HEAV.

Project Information: This is a Repair and Rehabilitation Project.

Construction Start: May 17, 2010

Construction Finish: August 2, 2010

Project Manager: Tim Burke

Design By: Arsee Engineers Inc.

Construction By:

Location: Central Drive

Map:

 

 

 

 

 

 

 