Project Title: David Ross Memorial Retaining Wall Repair
Project ID: 10906

Website Status Update

The functions previously performed by the Office of the University Architect (OUA) are now addressed by Physical and Capital Planning (P&CP), Project Management and Construction (PM&C), and Energy and Engineering Services (EES). The P&CP website is available here.  The Energy and Engineering Services website is available here. A new PM&C website is currently under development, however, essential information will be maintained in this location until the new website is launched. Thank you for your patience as these enhancements are completed.

Client: Office of the University Architect

Scope: Reset stone caps, caulk, repair, and tuckpoint stone retaining wall.

Note: This is a Repair and Rehabilitation project.

Construction Start: May 17, 2010

Construction Finish: July 30, 2010

Project Manager: Travis Robinson

Design & Engineering by: Arsee Engineers, Inc.

Construction Work by: Ziolkowski, Inc.

Location: Stadium Ave. at Slater Hill