Project Title: Earhart Hall East Entrance Exterior Concrete Sidewalk Replacement
Project ID: 10697

Website Status Update

The functions previously performed by the Office of the University Architect (OUA) are now addressed by Physical and Capital Planning (P&CP), Project Management and Construction (PM&C), and Energy and Engineering Services (EES). The P&CP website is available here.  The Energy and Engineering Services website is available here. A new PM&C website is currently under development, however, essential information will be maintained in this location until the new website is launched. Thank you for your patience as these enhancements are completed.

Client: Earhart Hall

Scope: Remove and replace approximately 1,700 sf of sidewalk at the east main entrance to ERHT.

Construction Start: May 17, 2010

Construction Finish: June 7, 2010

Project Manager: TJ Burns

Design & Engineering by: Physical Facilities

Construction Work by: Masonry Shop

Location: First St. and MacArthur Dr.