Project Title: Johnson Hall Section A Re-roof
Project ID: 10620
Website Status Update
The functions previously performed by the Office of the University Architect (OUA) are now addressed by Physical and Capital Planning (P&CP), Project Management and Construction (PM&C), and Energy and Engineering Services (EES). The P&CP website is available here. The Energy and Engineering Services website is available here. A new PM&C website is currently under development, however, essential information will be maintained in this location until the new website is launched. Thank you for your patience as these enhancements are completed.
Client: Office of the University Architect - Campus Planning
Scope: Remove existing roof and install new roof on section A.
Project Information: This is a Repair and Rehabilitation Project.
Construction Start: May 17, 2010
Construction Finish: August 2, 2010
Project Manager: Tim Burke
Design By: Etica Group
Construction By: AAA Roofing Co. Inc.
Location: Stadium Mall Dr. and 5th St.