Project Title: Harrison Hall Southeast Exterior Grounds Bike Hoop Installation
Project ID: 10499

Website Status Update

The functions previously performed by the Office of the University Architect (OUA) are now addressed by Physical and Capital Planning (P&CP), Project Management and Construction (PM&C), and Energy and Engineering Services (EES). The P&CP website is available here.  The Energy and Engineering Services website is available here. A new PM&C website is currently under development, however, essential information will be maintained in this location until the new website is launched. Thank you for your patience as these enhancements are completed.

Client: Harrison Hall

Scope: Install 20 bike hoops on existing concrete pad on northeast corner of HARR.

Construction Start: June 14, 2010

Construction Finish: July 12, 2010

Project Manager: Ken Jacobs

Design & Engineering by: Physical Facilities

Construction Work by: Masonry Shop

Location: MacArthur Dr. and First St.

 

 

 

 

 

 