Project Title: Hilltop Apartments Exterior Concrete Sidewalk and Stair Installation-2010
Project ID: 10467
Website Status Update
The functions previously performed by the Office of the University Architect (OUA) are now addressed by Physical and Capital Planning (P&CP), Project Management and Construction (PM&C), and Energy and Engineering Services (EES). The P&CP website is available here. The Energy and Engineering Services website is available here. A new PM&C website is currently under development, however, essential information will be maintained in this location until the new website is launched. Thank you for your patience as these enhancements are completed.
Client: Hilltop Apartments
Scope: Install a concrete sidewalk that connects from existing sidewalk between buildings 28 and 29 to access lower parking lot. In addition, install concrete steps from sidewalk to parking lot with side hand railing.
Construction Start: April 5, 2010
Construction Finish: May 28, 2010
Project Manager: Craig Dice
Design & Engineering by: Physical Facilities
Construction Work by: Masonry Shop
O&M Coordinator: n/a
O&M Crew Chief: n/a
Location: Tower Dr.
|