Project Title: MTHW Room 326 HVAC Replacement
Project ID: 10288
Website Status Update
The functions previously performed by the Office of the University Architect (OUA) are now addressed by Physical and Capital Planning (P&CP), Project Management and Construction (PM&C), and Energy and Engineering Services (EES). The P&CP website is available here. The Energy and Engineering Services website is available here. A new PM&C website is currently under development, however, essential information will be maintained in this location until the new website is launched. Thank you for your patience as these enhancements are completed.
Client: Consumer Sciences & Retailing
Scope: Replace existing HVAC system in room 326. New system will be installed in the attic.
Construction Start: March 2, 2010
Construction Finish: August 13, 2010
Project Manager: Ken Jacobs
Design & Engineering by: Physical Facilities
Construction Work by: Operations & Maintenance
O&M Coordinator: Doug Wagner
O&M Crew Chief: Darrell Burton
Location: State St. and University St.
Photos:


|